16.05.2018 OLO, A.S., WASTE INCINERATION PLANT, BRATISLAVA – REPAIR OF +120/2.39m CHIMNEY BODY

At present, a repair of the chimney body of the +120/2.39m chimney of OLO, a.s., waste incineration plant, Bratislava, is being carried out.

20.04.2018 CRH (SLOVAKIA), A.S., ROHOŽNÍK – COMPREHENSIVE RENOVATION OF +90/2.2 M CONCRETE CHIMNEY OF A WHITE-CEMENT ROTARY KILN, BUILT OF Z-SHAPED BLOCKS

On 20 April 2018, a comprehensive renovation of the concrete chimney of a white-cement rotating kiln made of Z-shaped blocks (+90 / 2.2 m) of CRH (Slovakia), a.s., Rohožník, was successfully completed.

20.12.2017 KNAUF Insulation s.r.o, Nová Baňa – Stage 2 of the reconstruction of reinforced-concrete +130 m chimney

On 20 December 2017, we successfully handed over the second stage of the reconstruction of the monolithic reinforced-concrete three-component +130/5.7m chimney of KNAUF Insulation s.r.o, Nová Baňa, within the agreed deadline.

24.10.2017 Tepláreň Košice, a.s., Košice – TEKO I +98.80 m Chimney Structural Repair

At present, the next stage of the repair of the reinforced-concrete multi-component +99.80 / 4.50 m TEKO I chimney made of building blocks is being carried out. The repair started in the second half of 2016 and its completion is scheduled to May 2018.

04.08.2017 Zvolenská Teplárenská, a.s., Zvolen – Repair of the Reinforced-Concrete Monolithic Partially Three-Component +180m Chimney

At the beginning of August 2017, we completed work on the repair of a 180m reinforced-concrete chimney of Zvolenská teplárenská, a.s..